Rock Solid Trail Contracting will begin their work on Butter Gap in January of 2024 and we can’t wait! To the left is the proposed construction plan. Below is the outline of the phased construction approach, and we’ll continue to keep the community updated as progress continues!
Butter Gap Construction Phase I
● Cedar Rock Decommission
● Build Upper Butter; constructed counterclockwise (plan to open new trail prior to decommissioning of current trail)
Butter Gap Construction Phase II
● Middle Butter Heavy Maintenance
Butter Gap Construction Phase III
● Build Lower Butter Hike/Bike Trail (plan to open new trail prior to decommissioning of current trail)
● Build Lower Butter to Cat Gap Hike Only Connector